Traffic Management

Project Status Contact
Tully Road Safety Improvement Project Fact Sheet Consultant contract agreement signed by Mark Tomas Company Inc. Project to be designed concurrently with the Carver/Bangs-Pelandale/Snyder Bike Trail System project. Project kick-off meeting anticipated in Fall 2018. Phillip Soares
Task Force Coordination to Establish School Safety Needs Fact Sheet
Staff has coordinated with Sylvan Union School District to perform site visit once school year begins in August. Staff is participating in planning committee with Community Pedestrian and Bicycle Safety Training Program (CPBST) through California Walks at Fremont Elementary School. Staff will participate in future workshops at the end of August. Sandeep Sandhu
Orville Wright Elementary School - Improve Traffic Flow and Safety Fact Sheet Design 0% complete. Survey work has been requested. Anticipate starting design late August 2018. Michael Sacuskie
Replace 120 Obsolete Traffic Controllers Received approximately 72 controllers. Waiting on rest of shipment for controllers and ethernet switches. Meeting with supplier and IT to prepare game plan for addressing as installation will occur soon. Mark Murphy
Emergency Vehicle Preemption Going to Economic Development Committee on August 8, 2018 to award bid. Mark Murphy
New Traffic Signals (Floyd Ave./Millbrook Ave., Prescott Rd./Mt. Vernon, Roselle Ave./Belharbour Construction is complete. Mark Murphy
Upgrade Traffic Signals (9th/B St., 7th/G St., 7th/H ST., 7th/I St. Intersections) Under design. Project is expected to go out to bid Fall 2018 of 2018. Mark Murphy
System Safety Analysis Report Program Fact Sheet Consultant contract awarded to Fehr and Peers on June 5, 2018. Kick-off meeting with Fehr & Peers scheduled for mid. August 2018. Sandeep Sandhu