Projects Fiscal Year 2017-2018

Project Quarterly Updates

Bike and Pedestrian

Project Status Contact
MJC Phase II Bike Path Fact Sheet Completed Michael Sacuskie
Active Transportation Plan (non-Motorized) Fact Sheet Consultant is currently collecting data. Phillip Soares
Active Transportation Plan III (Paradise Rd.) Fact Sheet Traffic study is complete. Staff will forward the study and grant acceptance at the 10/10/18 EDC Council Committee at the King-Kennedy Center (5:30pm) for approval. Phillip Soares
Carver/Bangs - Pelandale/Snyder Bike Trail System Fact Sheet Anticipate completing design by October 2018 and posting project bid in winter 2018/19. Construct project summer 2019 with Tully Road Safety Improvements project. Phillip Soares

Local Streets and Roads

Project Status Contact
Lakewood Neighborhood Street Improvement Fact Sheet Project is under construction. Anticipate construction to be completed end of the month December 2018. Michael Sacuskie
Standiford Pavement Rehabilitation Fact Sheet Project is under construction. Anticipate construction to be completed end of the month December 2018. Phillip Soares
Carpenter Road Street Improvements Fact Sheet Contractor has finished street paving and will soon be placing striping and installing traffic signage. Chuck Covolo
Wylie Dr., Floyd Ave., and Carver Ave. Street Improvements (Collector Streets) Fact Sheet Preliminary site investigation is complete. Project is under design. Michael Sacuskie

Traffic Managment

Project Status Contact
Tully Road Safety Improvement Project Fact Sheet Project kick-off meeting held with Fehr and Peers and Mark Thomas Company Inc. on September 26, 2018. Consultant will begin design. Phillip Soares
Task Force Coordination to Establish School Safety Needs Fact Sheet Staff continues to coordinate school concerns and issues with the schools districts. Sandeep Sandhu
Orville Wright Elementary School - Improve Traffic Flow and Safety Fact Sheet Preliminary site investigation is complete. Project is under design. Michael Sacuskie
System Safety Analysis Report Program Fact Sheet Consultant is working on collecting collision data and mapping with the City's GIS files. Sandeep Sandhu
Replace 120 Obsolete Traffic Controllers Have installed approximately 30 new controllers along Pelandale Avenue (8), Tully Road (10), College Avenue (5), and Coffee Road (7). Next corridors for controllers will be Dale Road and all of downtown. Change order for new conflict monitors going to council on October 23, 2018. Scott Collins
Emergency Vehicle Preemption Approved purchase order sent out 9/27/18. Awaiting manufacteruer to deliver units for installation. ​James Ashby
New Traffic Signals (Floyd Ave./Millbrook Ave., Prescott Rd./Mt. Vernon, Roselle Ave./Belharbour Construction is complete. Mark Murphy
Upgrade Traffic Signals (9th/B St., 7th/G St., 7th/H St., 7th/I St. Intersections Project design is approx. 85% complete. Anticipate advertising project for bid in November 2018. Sandeep Sandhu